Short answer: Structural steel inspection is an independent check that steel members, welds and high-strength bolts are fabricated and erected the way the approved plans say. In California, the 2025 California Building Code (CBC) Section 1705.2.1 requires special inspection of structural steel under the quality assurance requirements of AISC 360. The owner, not the contractor, hires the inspection agency, and the inspector reports to the building official.
Key takeaways
- The 2025 CBC sends structural steel inspection to AISC 360. Steel deck, joists, stainless steel and metal buildings each have their own rule in Section 1705.2.
- The owner or the owner’s agent hires the special inspector. The contractor can’t (CBC 1704.2).
- Shop welding is inspected during fabrication unless the shop is an approved fabricator (CBC 1704.2.5).
- In Los Angeles, a steel deputy needs current ICC S1 (Structural Steel and Bolting) and S2 (Structural Welding) certifications.
- Every inspection ends in reports, and a final report goes to the building official (CBC 1704.2.4).
What is structural steel inspection?
Structural steel inspection, often called steel special inspection or deputy inspection, is quality assurance done by an approved agency the owner hires. It sits on top of the city’s own inspections: the 2025 CBC, Section 1704.2, says special inspections and tests are in addition to the inspections by the building official.
For structural steel, Section 1705.2.1 points to the quality assurance inspection requirements of AISC 360, the American Institute of Steel Construction’s Specification for Structural Steel Buildings. Welding is judged against the AWS D1 welding codes, and bolted connections against the specification your plans name.
A few terms you’ll hear:
- Special inspector or deputy inspector: the certified person who watches and checks the work. “Deputy” is the term Los Angeles and many Southern California cities use.
- Approved agency: the inspection firm the building official accepts.
- Statement of special inspections: the list, prepared by your engineer or architect, of which items need special inspection on your job.
Which steel work needs special inspection
| Steel work | 2025 CBC section | Inspected per |
|---|---|---|
| Structural steel (beams, columns, braces, connections) | 1705.2.1 | AISC 360 quality assurance requirements |
| Structural stainless steel | 1705.2.2 | AISC 370 |
| Cold-formed steel floor and roof deck | 1705.2.3 | SDI QA/QC |
| Open-web steel joists and joist girders | 1705.2.4 and Table 1705.2.4 | Periodic inspection of end connections (welded or bolted) and bridging |
| Cold-formed steel trusses spanning 60 feet or more | 1705.2.5 | Section 1705.2.5 |
| Metal building systems | 1705.2.6 and Table 1705.2.6 | Periodic inspection of flange braces, purlins and girts, their bracing, and X-bracing |
| Steel in the seismic force-resisting system (Seismic Design Category B to F) | 1705.13.1.1 | AISC 341 quality assurance requirements |
Two exceptions are worth knowing:
- No welding, cutting or heating in the shop. Section 1705.2 waives special inspection of the fabrication process when fabrication for the whole building includes no welding, thermal cutting or heating of any kind. The fabricator must instead submit a material-control procedure that keeps the grade of the main steel members traceable.
- Some seismic steel in Seismic Design Category B or C. Section 1705.13.1.1 drops seismic special inspection where the design used the R value for “steel systems not specifically detailed for seismic resistance.” Your engineer knows which applies.
Hospitals and other projects under OSHPD (now HCAI) follow stricter amended rules in the same chapter.
Who hires the inspector, and who reads the reports

- Statement of special inspections. The registered design professional in responsible charge prepares it, and it goes in with the permit (CBC 1704.3).
- The owner hires the agency. The owner or the owner’s authorized agent, other than the contractor, employs the approved agency (CBC 1704.2). That keeps the inspector independent of the people doing the work.
- Reports go to two places. The agency sends reports to the building official and to the design professional in responsible charge (CBC 1704.2.4).
- Problems go to the contractor first. Discrepancies are brought to the contractor right away. If they aren’t fixed, the inspector reports them to the building official and the design professional before that phase of work is finished.
- Final report. A final report covering the required inspections and the correction of any discrepancies goes to the building official, at a point agreed before work starts.
Shop vs. field: where steel gets inspected
Most structural steel is welded and cut in a fabrication shop, then bolted and field-welded on site. The code treats the two places differently.
- In the shop: Section 1704.2.5 requires special inspection during fabrication of structural members built in a fabricator’s shop. The exception is a fabricator approved to work without special inspection (Section 1704.2.5.1). Approval is based on the shop’s written procedures and quality control manuals, with periodic audits. When the work is done, the approved fabricator gives the owner a certificate of compliance for the building official.
- On site: erection, field bolting, field welding, deck attachment and joist connections are inspected on site as your statement of special inspections lists them.
Ask early which shop your steel comes from. If it isn’t an approved fabricator, the inspector has to visit the shop during fabrication, and that needs to be on the schedule.
What the inspector checks
The exact task list comes from AISC 360 (and AISC 341 for seismic systems), applied to your plans. In practice the work falls into four groups:
| Area | What gets checked |
|---|---|
| Materials | Steel, bolts and filler metal match the approved plans and specs, and material is traceable |
| Welding | Procedures and welder qualifications, joint fit-up, the welding itself, finished weld size and appearance, and nondestructive testing where required |
| High-strength bolting | Bolt assemblies and storage, the installation method used, and that connections are tightened as specified |
| Erection details | Members, bracing, deck and joist connections installed as shown on the approved drawings |
For OSHPD-regulated buildings, the CBC spells some of this out (Section 1705.2.7): the welding inspector must have at least the qualifications of an AWS Certified Welding Inspector (CWI), keep a daily record of welder identification marks, defective welds and how they were corrected, and furnish a verified report that the welding conforms to AWS D1.1, D1.3, D1.4, D1.6, D1.8 and the approved plans.
Los Angeles: who can be your steel deputy
In the City of Los Angeles, steel deputies are licensed by LADBS under the Steel Construction (SC) class, which covers structural steel, welding, high-strength bolting and cold-formed steel framing. Per LADBS Information Bulletin P/BC 2026-035 (revised July 17, 2026), an SC deputy must hold:
- Current ICC certification S1 Structural Steel and Bolting, and
- Current ICC certification S2 Structural Welding,
- plus a high school diploma or equivalent and one of the experience paths listed in the bulletin.
Other Southern California cities set their own registration rules, so check with the building department that issued your permit.
Pre-steel checklist for builders
Run through this before the first steel delivery:
- The statement of special inspections lists every steel item on your job: structural steel, deck, joists and seismic frames.
- The owner or owner’s agent has hired the inspection agency, and the building official knows who it is.
- You know whether the fabricator is approved to work without special inspection. If not, shop visits are scheduled.
- Approved plans, shop drawings and welding procedures are on site for the inspector.
- Mill certificates and bolt certifications are ready to show.
- Your schedule leaves room for inspection before welds or connections are covered by deck, finishes or spray fireproofing.
- You know who on your team receives discrepancy notices and how fast they get fixed.
Example: what one small steel job might need
Example only, not a real project. Your plans decide. A two-story steel-frame retail building in Los Angeles with moment frames, metal roof deck and open-web joists, fabricated by a shop that is not an approved fabricator:
| Item | Where | Rule |
|---|---|---|
| Shop welding of frame connections | Fabrication shop | CBC 1704.2.5, AISC 360 |
| Field bolting and field welding | Jobsite | CBC 1705.2.1, AISC 360 |
| Moment frames (seismic force-resisting system) | Shop and jobsite | CBC 1705.13.1.1, AISC 341 |
| Roof deck attachment | Jobsite | CBC 1705.2.3, SDI QA/QC |
| Joist end connections and bridging | Jobsite (periodic) | CBC Table 1705.2.4 |
| Final report | To LADBS | CBC 1704.2.4 |
Requirements vary by jurisdiction, code edition and permit. Your approved construction documents and the building official have the final word.
Frequently asked questions
Who hires the structural steel inspector?
The owner or the owner’s authorized agent hires the approved inspection agency, and it can’t be the contractor. That rule is in 2025 CBC Section 1704.2. The agency then reports to the building official and the design professional.
Is special inspection needed if the steel comes from an approved fabricator?
Inspection during fabrication isn’t required in an approved fabricator’s shop (CBC 1704.2.5.1). The fabricator submits a certificate of compliance instead. Field erection, bolting and welding on site are still inspected.
What certifications does a steel deputy inspector need in Los Angeles?
LADBS requires current ICC S1 Structural Steel and Bolting and S2 Structural Welding certifications for the Steel Construction (SC) deputy license, per Information Bulletin P/BC 2026-035. Other cities set their own rules.
Is a special inspection the same as the city inspection?
No. The CBC says special inspections are in addition to the building official’s own inspections. Your city inspector still makes their inspections, and the special inspector checks the detailed steel work the code assigns to special inspection.
What happens if the inspector finds a problem?
The inspector tells the contractor right away so it can be fixed. If it isn’t corrected, the inspector reports it to the building official and the design professional before that phase of work is finished (CBC 1704.2.4).